Saturday, Aug 08, 2020 | Last Update : 01:40 PM IST

136th Day Of Lockdown

Maharashtra49026232728117092 Tamil Nadu2850242275754690 Andhra Pradesh2069601204641842 Karnataka164924842322998 Delhi1427231282324082 Uttar Pradesh113378668341981 West Bengal89666630601954 Telangana7525753239601 Bihar7179446294400 Gujarat68855517922604 Assam5549737225132 Rajasthan4941835186763 Odisha4255028698292 Haryana4005433444467 Madhya Pradesh3729827621962 Kerala3170019147103 Jammu and Kashmir2392716218449 Punjab1901512491462 Jharkhand140705199129 Chhatisgarh10109761369 Uttarakhand8008484795 Goa7075511460 Tripura5520367528 Puducherry4147253758 Manipur301818147 Himachal Pradesh2879171013 Nagaland24056594 Arunachal Pradesh179011053 Chandigarh120671520 Meghalaya9173305 Sikkim7832971 Mizoram5022820
  India   All India  14 Mar 2018  India’s own GPS 7 years late despite 90 per cent of funds allocated spent

India’s own GPS 7 years late despite 90 per cent of funds allocated spent

THE ASIAN AGE. | SANJIB KR BARUAH
Published : Mar 14, 2018, 1:56 am IST
Updated : Mar 14, 2018, 6:36 am IST

Approved by the government way back in May 2006, the NAVIC system should have been up and running by 2011.

The national auditor in its report summed up several causes for the delay.
 The national auditor in its report summed up several causes for the delay.

NEW DELHI: An independent satellite system called Navigation with Indian Constellation (NAVIC), often touted as the Indian equivalent of GPS and expected to immensely benefit the Army, Navy and the IAF besides the security and paramilitary forces, is yet to see the light of the day despite having spent 90 per cent of the funds allotted for the project that is already running more than seven years behind schedule.

Approved by the government way back in May 2006, the NAVIC system should have been up and running by 2011.

 

Once erected, the veritable “eye-in-the-sky” can keep watch over the entire country as well its surrounding region extending upto 1,500 km, including areas inside Pakistan, China and the Indian Ocean region, where military activity and movements have picked up of late.

The notable aspect is that about 90 per cent of the funds allotted for the project or about Rs 1,284 crore of the total cost of Rs 1,420 crore has already been spent till now even as the project is yet to see the light of the day, a CAG report tabled in parliament on Tuesday said.

“The development and deployment of NAVIC constellation, ground infrastructure, navigation, safety and certification, verification software was expected to be completed within five to six years from the date of approval of the project i.e. by December 2011,” the CAG stated.

 

The national auditor in its report summed up several causes for the delay. “Sites not being ready, revisions in the technical specifications, non-compliance with contract specifications by the contractor, administrative reasons, delays in shipment and delays in completion of civil works,” the CAG listed.

The NAVIC system is to comprise seven satellites that have already been launched between July 2013 and April 2016.

With the seven satellites already been placed in their respective positions in space, they remained idle from a period ranging from for 14 months to four years.

With the life of navigational satellite estimated at 10-12 years, the delay in operationalising the NAVIC programme would limit the duration of their utility, the CAG said, adding that a lot of ground facilities created for the programme also remained unutilised.

 

As of December 2017, the reply of the Department of Space (DOS) to various queries that the CAG raised was still awaited, the CAG said.

Tags: navic, department of space