Sunday, May 19, 2024 | Last Update : 06:06 AM IST

  Metros   Mumbai  12 Nov 2017  Decade on, no end in sight for project

Decade on, no end in sight for project

THE ASIAN AGE.
Published : Nov 12, 2017, 1:36 am IST
Updated : Nov 12, 2017, 1:36 am IST

According to civic officials they have not received any single penny from the Centre despite having received several assurances.

Some of the buildings IN Mahul are fully occupied by PAPs. (Photo: Shripad Naik)
 Some of the buildings IN Mahul are fully occupied by PAPs. (Photo: Shripad Naik)

Mumbai: In spite of more than a decade having elapsed, the Brihanmumbai storm water disposal system (BRIMSTOWAD) project is still incomplete. Though the works of phase 1 have been completed, nearly half of phase 2, which consists of 38 works, is yet to be completed.  In the past nine years, 18 of 20 works under phase 1 undertaken by the Brihanmumbai Municipal Corporation (BMC) have been completed while two are in progress.

Around 5,000 to 6,000 people are expected to be affected due to BRIMSTOWAD project work but the civic body is yet to verify their eligibility and their rehabilitation is still pending.

The cost of the project, which was supposed to be completed by 2015, has zoomed to Rs 4,000 crore from its original estimate of Rs 1,200 crore in the past 9 years.

According to civic officials they have not received any single penny from the Centre despite having received several assurances. According to a top civic official, the BMC requires an additional Rs 2,800 crore to complete this project due to several reasons. For this, the civic body has sent a revised report to the Centre. However, there has been no response as of now.

Tags: brimstowad, brihanmumbai municipal corporation