Saturday, Aug 15, 2020 | Last Update : 05:20 AM IST

142nd Day Of Lockdown

Maharashtra54831338184318650 Tamil Nadu3145202563135278 Andhra Pradesh2641421709242378 Karnataka1964941126333511 Delhi1494601343184167 Uttar Pradesh140775887862280 West Bengal98459671202059 Telangana8647563074665 Bihar8274154139450 Gujarat71064542382652 Assam5883842326145 Rajasthan5249738235789 Odisha4592731785321 Haryana4163534781483 Madhya Pradesh3902529020996 Kerala3811424922127 Jammu and Kashmir2489717003472 Punjab2390315319586 Jharkhand185168998177 Chhatisgarh12148880996 Uttarakhand96326134125 Goa871259575 Tripura6161417641 Puducherry5382320187 Manipur3752204411 Himachal Pradesh3371218114 Nagaland30119738 Arunachal Pradesh223115923 Chandigarh1595100425 Meghalaya11154986 Sikkim9105101 Mizoram6203230
  Business   Companies  19 Nov 2019  BHEL commissions pumping units for irrigation scheme in Telangana

BHEL commissions pumping units for irrigation scheme in Telangana

PTI
Published : Nov 19, 2019, 9:40 am IST
Updated : Nov 19, 2019, 9:40 am IST

BHEL is also carrying out comprehensive renovation and modernisation of more than 684 MW hydro projects across the country.

More than 500 hydroelectric generating sets of various ratings have been ordered on BHEL with a cumulative capacity of more than 30,000 MW.
 More than 500 hydroelectric generating sets of various ratings have been ordered on BHEL with a cumulative capacity of more than 30,000 MW.

Bhopal: Public sector major, Bharat Heavy Electricals Ltd (BHEL), on Monday announced it has commissioned additional pumping units for Package-6 and Package-8 of Kaleshwaram Lift Irrigation Scheme in Telangana.

With the commissioning of two pumping unitseach at package-6 (7x116 MW) and package-8 (7x139 MW), it has successfully commissioned all 14 pumping units of these packages within a record period of six months, an official release said.

 

These are very large size pump sets with each pump designed to lift 89 cusecs of water against a head of 100 to 125 metres, it said. Kaleshwaram is a greenfield irrigation project developed by the irrigation department of the Telangana government. Package 6 is located in Peddapalli district and Package 8 is located in Karimnagar district of Telangana.

The equipment has been supplied from BHELs manufacturing units at Bhopal, Rudrapur, Bengaluru and Jhansi, while the supervision of erection and commissioning at the site was carried out by the companys power sector southern region division, Chennai.

 In Telangana, BHEL has so far commissioned 39 pump- motor sets of various ratings aggregating to 2,306 MW. In addition,BHEL is presently executing another 26 pump-motor sets totalling to 3,572 MW for various lift irrigation schemes.

 

BHEL is presently executing hydroelectric projects of more than 6,000 MW, which includes 2,910 MW of projects within the country and 3,184 MW abroad. Besides, BHEL is also carrying out comprehensive renovation and modernisation of more than 684 MW hydro projects across the country.

Significantly, more than 500 hydroelectric generating sets of various ratings have been ordered on BHEL with a cumulative capacity of more than 30,000 MW, including 6,680 MW for overseasprojects.

BHELs hydro plants are running successfully in India as well as in Afghanistan, Azerbaijan, Bhutan, Malaysia, Taiwan, Tajikistan, Rwanda, Thailand, New Zealand, Nepal and Vietnam. 

 

Tags: bhel, power plant, irrigation scheme, telangana
Location: India, Madhya Pradesh, Bhopal